The site ready for layout - 11/23/15
First bite in digging the footers - 11/23/15
Digging the footers - 11/23/15
Pouring the footers - 11/24/15
Quality Concrete on the pouring - 11/24/15
The footers completed - 11/24/15
David, Stephen and L.C. Cole, Blockmasons, doing the blockwork in preparation for the building pad - 12/7/2015
Ready to pour building pad - 12/14/2015
Gravel backfilling by Quality Concrete in preparation for pouring of the pad next week - 12/9/2015
Pouring of the floor by Quality Concrete - 12/16/2015
Finishing of the Floor by Quality Concrete - 12/16/2015
Interior of the new auditorium - 1/11/2016
Setting of the last truss - 1/11/2016
Roof sheeting finished today by Michael Owens and crew - 1/14/2016
Facing the platform in the auditorium - 1/27/2016
"In the dry," front overhang built, and all of the HVAC, Plumbing, and Electrical being roughed in inside - 1/28/2016
Y's Roofing Contractors finishing the shingles on Friday evening - 2/5/2016
Stacked Stone being applied to the exterior of the sides and front of the building - 2/16/2016
All rough-in inspections for the framing, HVAC, electrical, and plumbing passed yesterday and the application of the spray in foam insulation began today - 2/16/2016
Exterior View of Latest Progress: Concrete Walks, HC Parking Spots, and Guttering Installed - 5/10/2016
Interior of Auditorium and Fellowship Hall Progress - 5/10/2016
Interior of Auditorium and Fellowship Hall Progress - 5/10/2016